Linwood Elementary, Kansas

For this project the HVAC contractor, Temp- Con Inc, was tasked with installing HVAC Ductwork, Refrigeration Piping, and Ceiling Cassettes at an elementary school in Linwood Elementary in Kansas.

Linwood Elementary, Kansas
Date: 7 September 2022
  • Building Type: School
  • Main Contractor: Temp-Con, Inc.
  • Building Structure: Steel Beams
  • Services: HVAC Ductwork, Refrigeration Piping

 

“We’ve used a different cable system in the past and Gripple saves more time and is easier to adjust than other systems. We really saved on the piping side by not having to cut rod and messing with all of that, huge savings”

Danny Todd, General Superintendent

 

For this project the HVAC contractor, Temp- Con Inc, was tasked with installing HVAC Ductwork, Refrigeration Piping, and Ceiling Cassettes at an elementary school in Linwood Elementary in Kansas. 

Prior to this project the contractor had no previous experience using Gripple products and had been using a competitor product. Temp-Con’s project managers were introduced to Gripple at a contractor event and decided to give the products a try. 

To start off the project the contractor utilized Gripple’s take-off service. This included pricing, estimates, product information sheets, technical drawings and a labor savings breakdown. Once they started using Gripple products, they found that Gripple eliminated the need for cutting threaded rod and strut and made the installation time 33% faster. 

Gripple Solution Traditional Method
Overview UniGrip / Universal Bracket / Duct Trapeze / GCS Clamp / Butterfly Trapeze / Express Hanger Threaded Rod & Strut
Installation Time (hr) 533 hours 1,316 hours